A meeting room with a rough wooden table, white chairs and a floor to ceiling window overlooking the city.

Huawei, a regional R&D campus in Tashkent.

3,200 sqm for engineers and developers - laboratory bays, collaboration spaces, a demonstration hall and campus infrastructure under one roof.

Tashkent
Location
Technology / R&D
Sector
3,200 sqm
Size
28 wks.
Timeline
A glass walled corridor with a lounge area visible through the partitions, furnished with a sofa and a floor lamp. A group of people at a wooden table with laptops and drinks in a room with open shelving.
The brief

A working environment and a technology showcase in one.

Huawei was opening a development and technology expertise centre in Tashkent for Central Asian markets. The space had to serve two very different scenarios - a productive working environment for engineering teams on the upper floor and a public showcase for demonstrating products to partners and government clients on the lower one.

An added requirement was engineering infrastructure with spare capacity for lab equipment and room to extend the cabling network without opening up the walls.

A desk with a desktop computer, a laptop and a flowering orchid by a window overlooking the city.
Approach

Campus logic - a public floor and a working floor.

The first floor is open and includes the reception, a 280 sqm demonstration hall with integrated AV systems and a conference zone for outside events. The second floor is closed and includes engineering open space blocks, six access controlled laboratory bays and a server room with its own cooling loop.

Category 6A structured cabling, dedicated power lines for equipment and a raised floor throughout every working zone leave room to reconfigure without construction work.

An open office floor with long desks where dozens of people work at laptops.
Key zones

A demo hall, laboratories and collaboration spaces.

The demonstration hall is the main public zone. Interactive Huawei Enterprise product stands are built into the architecture with no temporary fittings. The hall can be reconfigured in a single day whenever the product line up changes.

The working floor holds more than 160 engineering desks, collaboration zones with movable partitions, quiet booths for focused work and a coffee point on every wing.

A plant filled lounge with green velvet armchairs, where three people talk at a table by the window.
Result

28 weeks. The campus welcomed its first teams on time.

All six laboratory bays were handed over together with the main open space. The engineering systems passed Huawei's technical auditor with no remarks. The demonstration hall opened on the planned date, and the first partner event took place a week after handover.

The campus works as a single organism - the engineering environment and the public showcase do not compete for space, they complete each other.

A technology campus where the engineering team's working environment and the company's product showcase exist as two floors of the same building, with no compromise for either scenario.

A kitchen counter with pendant lights, a brass tap and fresh greens on the worktop.
Guidance

R&D environments - planning space for engineering teams.

A guide to designing technology campuses covers zoning, engineering requirements and the balance between collaboration and focus.

Read the guide
Tell us about your project

Have a similar brief?

We will put together a team, price the budget within a week and visit the site free of charge.